Network cutover readiness checklist

What to check before you change a live network or system. Most cutovers that go wrong were missing something simple: a rollback trigger nobody agreed, a site key nobody had, a test that left no evidence. This checklist covers the six areas we review before every cutover.

Why a checklist still matters

Experienced teams don't fail on the hard parts. They fail on the small things everyone assumed someone else had done. A short, shared checklist turns those assumptions into named owners and written answers, a day before the change instead of at 2 am.

Use it in your readiness meeting, a day or two before the window. Anything you can't tick is either fixed, accepted as a risk by the person who owns the go / no-go call, or a reason to move the date.

The checklist

1. Plan and method of procedure

  • Every step has an owner, a planned start time and an expected duration.
  • Dependencies and hold points are marked, with the person who releases each hold point.
  • The change window fits the plan, with time kept back for a rollback.
  • The pre-change state is captured: configurations backed up, baseline readings recorded.
  • Vendor and third-party steps are confirmed in writing, with names and phone numbers.

2. Testing

  • Pre-checks are written down and run the day before, and again on the day.
  • Each test has a pass criterion, not just "check it works".
  • Every test leaves evidence: a reading, a screenshot, a log or a signed record.
  • Customer-facing services are tested end to end, not just the links in between.
  • Someone who did not make the change confirms the acceptance tests.

3. Rollback

  • Clear trigger points: which result, or which time on the clock, means you roll back.
  • Rollback steps are written out in full, not "reverse the steps above".
  • Time to restore is estimated, and it fits inside the change window.
  • The rollback has been rehearsed or tested where that is practical.
  • The person who calls the rollback is named, and so is their backup.

4. Communications

  • Customers and users know what will happen, when, and what they will notice.
  • Operations, the NOC and on-call teams have the plan and the contact list.
  • One bridge or chat channel is set up for the night, run by one person.
  • Update times are agreed: for example every 30 minutes and at each hold point.
  • Messages are drafted in advance for success, for a rollback and for an overrun.

5. Sign-offs and authority

  • The change is approved through your change process (CAB or equivalent).
  • The go / no-go decision owner is named, and the criteria are written down.
  • Contract and client requirements are checked: notice periods, approvals and outage limits.
  • Everyone knows who can stop the work on safety grounds, and that they will be backed.

6. People and logistics

  • Site access, keys, inductions and permits are arranged for every site involved.
  • Spares, tools, test gear, cables and charged laptops are checked and on site.
  • There is a shift plan with breaks, so nobody runs the critical steps exhausted.
  • Risk assessments or SWMS are in place for the on-site work.
  • The contact list, with mobile numbers, is checked the day before.

Five red flags we see most often

  • "Rollback: reverse the above." If it isn't written step by step, it hasn't been thought through.
  • No time to restore. Without it you cannot know whether the window is big enough to fail safely.
  • Nobody owns the go / no-go call. On the night, the decision drifts to whoever is loudest or most tired.
  • Tests with no evidence. "Looked fine" is not an acceptance record, and it will not help the next shift.
  • The same people on shift for 14 hours or more. The riskiest steps often come last, when people are most tired.

Running the go / no-go call

  1. Status of every pre-check, read out against the plan, not from memory.
  2. Open risks and issues, each with an owner and a yes or no: do we proceed with it?
  3. Rollback confirmed: triggers, steps, time to restore and who calls it.
  4. People and sites ready: access, spares, shifts and contacts.
  5. The decision, made by the named owner and recorded with the time.

After the cutover

  • Keep watch. Agree a hypercare period with extra monitoring and a named contact.
  • Close it properly. Record the evidence, update the as-built records, and close the change.
  • Learn from it. A short lessons-learned session while it's fresh, written down for the next one.